How to deal with the electric control system failure of asphalt mixing plant?

March 24th, 2022 asphalt mixing plant,asphalt concrete,electric control system,sensor
Asphalt mixing plant refers to a complete set of equipment used for mass production of asphalt concrete. According to the mixing mode, it can be divided into forced intermittent type and continuous production type; According to the handling mode, it can be divided into fixed type, semi fixed type and mobile type.

The electric control system is the core component of the asphalt mixing plant. Once the electric control system fails, the asphalt mixing plant will not work, which will bring great trouble and loss. Therefore, if users use asphalt mixing plant, they must simply master some methods to deal with the faults of electric control system.

0324

When using the asphalt mixing plant, if the instrument display of the electric control system is inaccurate, the reason is likely to be the influence of external force on the weighing system, or the change of weighing zero position or weighing spacing caused by sensor drift error.
In the above situation, the user needs to first eliminate the external force of the electric control system of the asphalt mixing plant, and then calibrate the zero position of the weighing again. If the asphalt mixing plant is weighed by multiple sensors, the situation of eccentric load needs to be considered. If the state of eccentric load is found, it is likely that one of the sensors is damaged or the cable is loose and damaged. At this time, what users need to do is to replace the sensor and check the cable.
If the user encounters the batching accuracy problem of the electronic control system of the asphalt mixing plant, for example, in the batching process, the weighing value displayed by the controller is accurate, but the weighing value of the batching is not consistent with the setting, and the accuracy is beyond the allowable range. There are many reasons for this situation. The user must clarify the specific causes of the fault before it can be solved.